Capability

Planning & Scheduling

Baseline Schedule Development

Build a logic-linked programme the project can perform against: complete scope, real calendars, honest constraints, and a structure that can be updated.

Discuss Your Project View All Capabilities

C02 — The problem

The technical problem

A bar chart can look complete and still be unusable as a control instrument. Missing logic, decorative constraints, incomplete scope, calendars that do not match the contract, and a WBS the cost file cannot share all produce a file that cannot be updated honestly.

Baseline Schedule Development is the assignment to produce a programme that can survive progress, change, and recovery — including the planning basis, coding, milestones, and measurement hooks the later updates will need.

C03 — Engagement

When this capability is needed

  1. 01
    Contract mobilisation

    A baseline is required for approval or notice.

  2. 02
    Rejected submission

    The submitted programme failed review and must be rebuilt, not decorated.

  3. 03
    Re-baseline

    The live path no longer matches the authorised works and a new baseline is being considered.

  4. 04
    Control readiness

    Project controls cannot lock a time baseline because the file is not performable.

C04 — Scope / method

How the work is approached

Scope includes WBS alignment, activity definition, logic, calendars, constraints, milestones, coding, and a basis-of-schedule note. It is not schedule review of a third-party file (that is Schedule Review & Assurance) and not recovery of a slipped live programme (Recovery Scheduling).

  1. 01
    Lock the planning basis

    Contract dates, calendars, working hours, and coding before activity noise.

  2. 02
    Structure the WBS

    A breakdown schedule, cost, and change can share.

  3. 03
    Build logic-linked activities

    Remaining duration that can be calculated, with open ends and lags treated as risks not habits.

  4. 04
    Apply only justified constraints

    Contractual and physical constraints documented; convenience constraints removed.

  5. 05
    Code for control

    Activity IDs, control accounts, and milestones the update cycle can use.

  6. 06
    Issue for review

    Programme file plus basis of schedule, ready for assurance or approval.

C05 — Outputs

Typical deliverables

Typical deliverables
Output What it contains
Baseline CPM programme Logic-linked file used as the time baseline.
Basis of schedule Calendars, constraints, coding, and assumptions.
WBS / coding dictionary Structure shared with cost and change.
Milestone register Contractual and control milestones.
Baseline issue record Version submitted for approval.

C06 — Decision value

What this work is used to decide

Whether the proposed programme is performable enough to accept as the time baseline, return for correction, or reject. Acceptance is a management decision, not a promised project outcome.

C09 — Who we support

Who commonly needs this capability

C10 — Boundaries

Important distinctions

A baseline programme is not design certification, method-statement approval, or a guarantee of completion.

C11 — Next step

Discuss your project

If this is the technical problem you are facing, talk to Value Construction about the work, the records required, and what you would receive. Outcomes are not guaranteed.

Discuss Your Project

Scroll to Top