Capability

Planning & Scheduling

Schedule Risk Analysis

Test duration uncertainty on a logic-linked programme so completion exposure is visible before it is treated as a single date.

Discuss Your Project View All Capabilities

C02 — The problem

The technical problem

Deterministic programmes hide duration uncertainty. A P50 or ‘most likely’ date is presented as the plan, while weather, access, interfaces, and productivity sit in a separate register that never touches remaining duration.

Schedule Risk Analysis is a planning capability: duration ranges (and, where the model supports it, existence risk on activities) applied to the logic so leadership can see a range of completion outcomes and which activities drive the tail. This assignment is the schedule-side analysis. Joint cost-and-schedule quantitative models are a separate risk assignment.

C03 — Engagement

When this capability is needed

  1. 01
    Before baseline approval

    The date is sensitive and a single-point estimate is not enough.

  2. 02
    Major uncertainty

    Weather windows, shutdowns, or interface dates dominate remaining work.

  3. 03
    Governance / sanction

    A range is required alongside the deterministic programme.

  4. 04
    Recovery comparison

    Options need risk-adjusted dates, not only crash calendars.

C04 — Scope / method

How the work is approached

Schedule-focused quantitative treatment of duration uncertainty on a defined programme. Cost-only quantitative risk, qualitative registers, and Monte Carlo cost models are separate assignments.

  1. 01
    Fix the deterministic base

    A programme that can be calculated, not a broken file.

  2. 02
    Agree uncertainty inputs

    Duration ranges and discrete risks mapped to activities, with sources.

  3. 03
    Run the schedule risk model

    Iterations sufficient to describe the completion distribution.

  4. 04
    Identify drivers

    Which remaining activities and risks move the tail.

  5. 05
    Report the range

    Dates at agreed percentiles, with the deterministic date shown for comparison.

C05 — Outputs

Typical deliverables

Typical deliverables
Output What it contains
Schedule risk analysis report Method, inputs, and completion distribution.
Driver list Activities and risks that move the result.
Input register Ranges and assumptions used.
Comparison to the deterministic date So the single-point plan is not quietly replaced.

C06 — Decision value

What this work is used to decide

Whether to accept a completion date as a planning target, hold contingency in time, or change sequence before locking the baseline. The analysis does not guarantee a percentile date.

C09 — Who we support

Who commonly needs this capability

C10 — Boundaries

Important distinctions

Schedule risk analysis does not guarantee outcomes and is not a substitute for a live risk register or for commercial contingency decisions.

C11 — Next step

Discuss your project

If this is the technical problem you are facing, talk to Value Construction about the work, the records required, and what you would receive. Outcomes are not guaranteed.

Discuss Your Project

Scroll to Top