Capability

Planning & Scheduling

Recovery Scheduling

Recast remaining logic when the current path is no longer credible — options with time consequences, not a new slide date.

Discuss Your Project View All Capabilities

C02 — The problem

The technical problem

When a programme is late, the usual response is a new target date without a new sequence. Remaining work is compressed with lags and constraints until the bar lands on the old milestone.

Recovery Scheduling starts from remaining scope and remaining logic, then tests alternative sequences, resources, or work fronts that could change completion. Each option has time consequences that cost and commercial teams can price. It is not a claim for acceleration (that is a Claims assignment) and not a routine look-ahead (Short-Term Planning).

C03 — Engagement

When this capability is needed

  1. 01
    Forecast breach

    Completion or a contractual milestone is no longer achievable on the current path.

  2. 02
    Instruction to recover

    The employer or contractor requires a recovered programme.

  3. 03
    After major change

    Remaining works need a new sequence, not a painted date.

  4. 04
    Before commercial negotiation

    Parties need options, not a single unexplained crash.

C04 — Scope / method

How the work is approached

Options for remaining work: re-sequence, alternative work fronts, overtime or additional resources as scenarios — each with time effect. Commercial entitlement to acceleration or prolongation is out of scope unless separately instructed under Claims.

  1. 01
    Freeze remaining scope

    What is left to do, on current evidence.

  2. 02
    Explain why the current path fails

    Driving work, constraints, and interfaces.

  3. 03
    Build recovery options

    Sequence and resource scenarios, not slogan dates.

  4. 04
    Compare time consequences

    Effect on completion and intermediate milestones.

  5. 05
    Recommend an implementable path

    What would have to be instructed for the option to be real.

C05 — Outputs

Typical deliverables

Typical deliverables
Output What it contains
Recovery programme options Alternative remaining-work files or fragments.
Comparison of time consequences Dates and driving logic per option.
Implementation notes Instructions, interfaces, and assumptions each option needs.
Narrative Why the current path fails and what each option changes.

C06 — Decision value

What this work is used to decide

Which recovery option to instruct, reject, or take into commercial discussion. Selecting an option does not guarantee the date it shows.

C09 — Who we support

Who commonly needs this capability

C10 — Boundaries

Important distinctions

Recovery scheduling is planning, not an acceleration claim and not legal advice on who pays for the recovery.

C11 — Next step

Discuss your project

If this is the technical problem you are facing, talk to Value Construction about the work, the records required, and what you would receive. Outcomes are not guaranteed.

Discuss Your Project